The Bengaluru civic body’s Chief Engineer (SWDs) M Lokesh presented the action-taken report on the issue before the HC. The report stated that 2,666 encroachments on SWDs (‘Rajakaluves’) were identified out of which 2,052 were removed by October 11. Out of the remaining 614 encroachments, 110 issues were in various courts. A total of 504 encroachments were yet to be cleared.
Advocate G R Mohan argued that encroachments made by big builders and influential politicians were not cleared by the authorities.
During the hearing the HC was informed by the BBMP’s counsel that 50 per cent of the encroachments on the Begur lake has been cleared. The HC directed that an action taken report on the Begur lake encroachments should be filed before October 14.