Petitioner Mandarmoni Hoteliers’ Association stated that a notice dated November 11 was issued by the chairman of West Bengal State Coastal Zone Management Authority (WBCZMA) and district magistrate of Purba Medinipur to demolish and clean the illegal constructions by November 20 by hotels, resorts and homestays at Mandarmoni in terms of the order of National Green Tribunal (NGT) of May, 2022.
Passing the interim stay on demolition of the alleged illegal constructions near the sea beach at Mandarmoni on the Bay of Bengal coast, Justice Amrita Sinha directed that the notice of November 11 will not be given effect to till December 13 or until further order, whichever is earlier.
Petitioners contended that the Coastal Regulatory Zone (CRZ) in respect of West Bengal is yet to be published and in view of that, the same cannot be identified.
Related Articles
Advertisement
The court said that the matter is yet to be heard in detail and parties are to make arguments in support of their respective contentions.
Holding that there is an immediate threat of demolition of the constructions at Mandarmoni, Justice Sinha granted an interim stay on the order for demolition of the alleged illegal constructions.