Advertisement

CM issues direction to restore damaged crest gate of Tungabhadra reservoir in 3-4 days

05:24 PM Aug 13, 2024 | PTI |

Karnataka Chief Minister Siddaramaiah on Tuesday said he has asked officials and experts to fix within three to four days the damaged crest gate of Tungabhadra reservoir so that water from expected rains can be stored.

Advertisement

After inspecting the dam, he also assured that there is no need for farmers to worry.

“I’m confident that Tungabhadra dam will be filled once again and I will come to offer ‘Bagina’ (traditional thanksgiving to the river). No politics on this issue.”

One of the crest gates (19th gate) of the Tungabhadra reservoir in Koppal district was washed away after its chain link snapped on Friday midnight.

Following this the downstream areas were put on alert, as a huge quantity of water was being released.

Advertisement

“We were releasing water through ten gates, which included the 19th gate. The 19th gate got washed away after its chain link snapped…we have consulted dam safety experts and the repair works are on. Based on the advice of experts, the Tungabhadra Board will take appropriate decisions,” Siddaramaiah told reporters.

He assured that there won’t be any problem for farmers in the three states — Karnataka, Andhra Pradesh and Telangana, who have sown crops, as water is flowing through all the canals and there will be any damage to crops. “There is no need for farmers to worry.” “…from August 17-18 there are expectations of above normal rains. I have asked experts to complete the work in three to four days, so that we can store the water from the expected rains, as we need 90 tmcft of water for standing crops. The government is at it, we want to complete the work at the earliest and want to ensure that farmers don’t face any trouble. It is our responsibility,” he added.

The dam is managed by the Tungabhadra Board with representatives from Karnataka, Andhra Pradesh and Telangana government representatives being its members; the Central Water Commission (CWC) appointee is the Chairman.

Andhra Pradesh Minister of Finance Payyavula Keshav, Minister for Water Resources Development Nimmala Ramanaidu, also MPs and legislators from that state were present during the Chief Minister’s visit and his interaction with media.

Noting that the dam construction work began in 1948 and got completed in 1953, and from 1954 water is being released to canals, the Chief Minister said, “the dam is aged about 70 years. So far there was no chain link snap in this dam’s 33 gates, now it has happened for the first time in the 19th gate.” This year the dam had received 115 tmcft of water out of which 25 tmcft was released through canals for fields of farmers in Karnataka, Andhra Pradesh and Telangana, he said. “For the first crop, 90 tmcft water is required and the dam currently has 90 tmcft of water. As of today there won’t be any trouble for the first crop.” From the damaged 19th gate 35,000 cusecs water is flowing out, Siddaramaiah said, adding, “without reducing the water level, repair work cannot be done. We have to bring down the water level at the dam to 1,621 ft from 1,629 ft; when we do that 64 tmcft of water will remain in the dam and with that we will have to complete the repair work. ” It will take a minimum of four to five days for chain and gate to be installed and the repair work to be completed, he further said, adding that “The work has began since yesterday, gate will be ready tomorrow, Narayana Engineering, Hindustan Engineering and Jindal are involved in the work .” Noting that it is for the first time in 70 years the chain link has snapped, the Chief Minister, citing experts, said it has to be changed at least once in 50 years. “Now, based on expert advice, the board and all the three state governments — will follow things.” To a question as to who will be held responsible for the incident, Siddaramaiah said it will be looked into.

“The board maintains the dam, the board is headed by a Chief Engineer level officer appointed by the central government. Representatives of the Central Water Commission and all the three states are part of the board. Was there any fault of dereliction of duty on their part will be looked into,” he added.

Noting that a detailed project report (DPR) worth about Rs 15,000 crore has been prepared for the Navali balancing reservoir across Tungabhadra river, the Chief Minister said it has been sent to the board, which will seek the opinion of Andhra Pradesh and Telangana. “If they give their approval, we will start the project. It is a multi state dam ” Earlier speaking to reporters on his arrival, Siddaramaiah rejected opposition BJP’s criticism of his government being “irresponsible” in managing the dam, saying “the dam is managed by the board, whose head is appointed by the Government of India….I don’t want to do politics on this issue.”

Advertisement

Udayavani is now on Telegram. Click here to join our channel and stay updated with the latest news.

Next