As per sources, the coal-based power plant has been facing financial difficulties against the backdrop of a hike in coal prices in the market.
Coal prices have witnessed a three-fold jump in the international markets recently. Unlike many coal power stations in the country, UPCL mostly depends on imported coal for electricity generation. So the rise in coal prices has prompted the UPCL’s management to suspend the procurement of fuel, reports said.
UPCL has two 600MW electricity generating units installed. The state government procured power from the company only when there was a shortage.
Related Articles
Advertisement
Meanwhile, the coastal districts are being supplied with power procured from elsewhere. Sources in the Mangalore Electricity Supply Company (Mescom) officials said that there is no need for load shedding in the near future.