Contractors, who had assured project completion by the deadline in a formal agreement with local representatives at the police station, now face potential criminal charges for missing the deadline. Despite multiple instructions from the district administration, the pace of work remains sluggish.
Progress So Far
Currently, 80% of the girder alignment is complete, and one side of the bridge’s structure has taken shape. Tasks like installing the top cover, fabricating the central girder for the concrete road, and significant welding work remain pending.
Coordination Issues Between Departments
The lack of coordination between the National Highway Authority and the Railways has been a major roadblock. Though the girders were delivered a month ago, work did not commence immediately. Regular meetings led by district officials and representatives have failed to speed up the process due to delays in obtaining approvals from railway authorities.Bridge Specifications
- Length: 58 meters
- Width: 12.5 meters
- Pedestrian Pathways: 1.5 meters on both sides
- Material: 240 tons of steel for girder fabrication
Related Articles
Welding Work Underway
Advertisement
Currently, 7-8 workers are continuously engaged in welding tasks. Concrete slabs have been prepared for easier installation of the bridge, and prior structural components have been cleaned. Equipment for pulling the bridge into place is ready, but welding and girder assembly are still in progress.