The bridge was built in 1866-67 and was declared unsafe by an expert team of the Indian Institute of Technology Bombay (IITB) in 2018, though the movement of heavy vehicles on it was stopped in 2014 itself, officials said.
“The work of removing the top cement concrete layer began on Friday. The dismantling of the parapet, vertical columns and concrete of the corroded trough will follow,” the CR official said.
“Since the bridge runs over the tracks that see heavy suburban train traffic, we will carry out the demolition-dismantling work during night. We will also carry out the work during mega blocks (period when train movement is halted) operated on Sunday for routine maintenance,” he added.
Related Articles
Advertisement
The demolition of the entire bridge, which is a vital east-west link in south Mumbai, is likely to take three months, the CR official said.
The bridge was closed for all kinds of traffic last month following a meeting of railway, traffic police and civic officials, who took into consideration widespread cracks and corrosion on the structure.