NHPC to commission 2,000 MW hydropower project on Subansiri by March 2022

08:33 AM Dec 06, 2020 | Sowbhagya Lakshmi |

Guwahati: PSU major NHPC Ltd on Saturday said the 2,000 MW Subansiri hydropower project, which was stalled for nearly eight years due to intense protests by many groups in Assam, will be commissioned by March 2022.

Advertisement

Union power ministry”s secretary Sanjiv Nandan Sahai, Arunachal Pradesh chief secretary Naresh Kumar and the company”s chairman and managing director A K Singh visited the Subansiri Lower Hydro Electric project sites on Friday and inaugurated the restart of the power-house works, NHPC said in a statement.

“Later in the day, the power secretary held a review meeting wherein NHPC chief briefed about the various construction activities and downstream river protection works undertaken by the company. It was assured that the project shall be commissioned by March 2022,” it added.

Construction work of the ambitious project at Gerukamukh along the Assam-Arunachal Pradesh border on Subansiri river was halted from December 2011 to October 2019 due to protests by locals and many groups fearing about safety and the adverse impact on the downstream of the river.

According to a company estimate in January 2020, the cost of the mega project, which was scheduled to be commissioned in December 2012, had escalated to around Rs 20,000 crore.

Advertisement

The initial project cost was estimated at Rs 6,285 crore.

The Centre had allocated a total of Rs 11,000 crore as of December 2010 for construction of the dam.

Multiple committees were formed by the Assam government and the Centre to address the concern of the agitators. The outcomes of their reports varied from one to another.