The new railway line covers a distance of 104 kilometres including a 2 kilometre long underground tunnel. There are 13 railway stations exists between Bidar and Kalburgi stations. The railway route completed at a cost of Rs 1,542 crore against the previous estimate of Rs 369.7 crore.
The railway line took 16 years to complete its works against proposed duration of 5 years after then Union Railway Minister Bangaru Laxman laid foundation stone for the project in 2000.
Delay in land acquisition, hurdles faced during the construction of the railway line, lack of availability of financial support on time and others prevented the project to complete as projected earlier.