- Kundapur Flyover approach works near Shastri Circle (55% completed including structure)
- Pedestrian Underpass (PUP) at Ch 283+705 (50% ie structure completed and RE wall balance)
- Vehicular Underpass (VUP) at Ch 284+990 (50% ie structure completed and RE wall balance) \
- Pedestrian Underpass (PUP) at Ch 285+185 on the approaches of the VUP (Not yet started)
- Padubidri Minor Bridge approach works and counter-fort retaining wall (70% completed)
- Beejadi service road LHS service road at Ch 289+000 Saligrama service road on both sides not yet started at Ch 298+120
- Padubidri service road on both sides to be completed,” the letter stated.
Advertisement
Request to quickly complete pending highway works at Kundapur
01:34 AM Apr 05, 2020 | Team Udayavani |