Advertisement

Mumbai: British-era Carnac bridge dismantled; CR’s mainline, Harbour route restored

09:00 PM Nov 20, 2022 | PTI |

Mumbai: Central Railway managed to dismantle the British-era Carnac bridge between CSMT and Masjid stations in Mumbai before time on Sunday after operating a 27-hour traffic block that was supposed to end at 2 am on Monday, officials said here.

Advertisement

The block on all suburban and mainline tracks as well the ones in the yard between CSMT and Byculla and CSMT and Wadala was in place from 11pm on Saturday to 2am on Monday.

”However, the first train departed from CSMT for Thane at 3:50 pm on Sunday, passing the Carnac Bridge dismantling site at 4 pm. Harbour line was restored by 7 pm. The work on seventh line and yard are in progress and will be completed before the scheduled plan,” an official said.

He said removal of pathways in the available corridor margins before the block day and standby cranes helped to complete the work before time.

Central Railway general manager Anil Kumar Lahoti said, ”It was a huge and challenging task as traffic on all lines and CSMT stations were completely shut. The extensive preparatory work, innovative and meticulous planning, and coordination with local civic bodies enabled us to complete this enormous task ahead of schedule.”

Advertisement

The mega traffic block was also utilised to carry out a large number of other maintenance works involving tracks, overhead equipment (OHE), signalling in shadow block, which saved about 900 hours of future block period for the railways, he added.

The official said helpdesks were set up at various stations and continuous announcements were made about the schedule of express and suburban trains for the convenience of passengers.

He said CR appreciated the support of passengers and its counterpart Western Railway for operating suburban trains at full capacity during the weekend as well as civic authorities for running additional number of buses during the block period. The bridge was built in 1866-67 and was declared unsafe by an expert team of the Indian Institute of Technology Bombay (IITB) in 2018, though the movement of heavy vehicles on it was stopped in 2014 itself.

Advertisement

Udayavani is now on Telegram. Click here to join our channel and stay updated with the latest news.

Next